
View the
Greenville Southwest Bypass
Corridor Map
Click Here
To View Map (1.5 Mb)
Check out the NCDOT Website for future updates:
NCDOT
For More Information
Please Call the
(919) 733-7844
ext. 333
|
Greenville Southwest Bypass Corridor Update
(Improvements to NC 11 and US 264 Business)
(TIP NO. R-2250)
SCHEDULE FOR FINAL ENVIRONMENTAL IMPACT STATEMENT (FEIS)/RECORD OF DECISION (ROD)
- February 26, 2001 -- Project Notice to Proceed
- February 2001 -- Purpose and Need - Concurrence Point 1
- February 2005 -- Alternatives for Detailed Study - Concurrence Point 2
October 2005 -- Obtain Concurrence Point 2A
- July 2006 -- Complete Draft Environmental Document
- September 2006 -- Corridor Public Hearing
- November 2006 -- Obtain Concurrence Point 3
- June 2007 -- Obtain Concurrence Point 4A
- December 2007 -- Final Environmental Impact Statement (FEIS)
- August 2008 -- Record of Decision - ROD
- Fall 2008 -- Design Public Hearing
- Spring 2009 -- Right of Way Acquisition
- After 2015 -- Construction
For more information
Please visit the NCDOT Project website for current project information. The website included information pertaining to the environmental impact statement, a project schedule and a Frequently Asked Questions section. You will also find maps, newsletters and information about up-coming meetings and public hearings. If you are interested, there is also a mailing list to join if you would like up-to-date information sent to you.
www.ncdot.org/projects/greenville
|